Nuclear News Weekly Roundup - 06/18 - 06/22

Sanmen Unit 1 reaches first criticality and Haiyang Unit 1 approved for first fuel load, both crossing major milestones

Sanmen Unit 1 reached its first criticality on June 22nd and is expected to enter commercial operation later this year. Haiyang Unit 1 received approval for its first fuel load one day earlier, on June 21st and is expected to enter commercial operation by Q4 2018 or Q1 2019 at the latest.

 

Hongyanhe Unit 5’s steam generator installed

Recently, with the smooth installation of Hongyanhe Unit 5’s third steam generator on its vertical support, all 3 of the unit’s steam generators were officially installed in the reactor building. During the lifting process, China Nuclear Industry 23 Construction Co., Ltd. completed rings 1, 2, and 3 on May 3rd, May 24th and June 10th, respectively, which laid the foundation for the consequent main pipe welding.

 

All hydraulic components of Fuqing Unit 5’s RCPs delivered to site

On June 14th, the third and final RCP hydraulic assembly for CNNC’s Hualong One Demonstration project were delivered to Fuqing Unit 5’s site.

 

NNSA press conference on Taishan progress: the world’s first EPR will reach grid connection in July

The National Nuclear Safety Administration convened a press conference to discuss the progress of the Taishan nuclear power plant. In April, the plant received approval from the NNSA to begin its fuel loading, in the beginning of June passed inspection and achieved its first criticality, and now, is currently in the low power test phase. The plant is expected to connect to the external power grid in July and enter full power operation in the third quarter.    

 

NPP Safety Grade Electric Equipment Anti-Seismic Performance Authentication (核电厂安全级电气设备抗震鉴定) national standards released, coming into effect on December 1st

 

Dongfang Electric signed strategic cooperation framework agreement with NPIC

On June 19th, Dongfang Electric Company and the Nuclear Power Institute of China (NPIC) signed a strategic cooperation framework agreement. The two sides intend to deepen their strategic cooperation relationship regarding the nuclear power industry chain and build a platform for project cooperation. Before the signing ceremony, the two sides held friendly discussions on deepening cooperation and promoting independent innovation of nuclear power.

 

Major Milestones for Chinese AP1000s: Sanmen I has First Criticality, Haiyang I Approved for First Fuel Load

First Criticality at Sanmen I

On June 22, 2018, Chinese media reported that the world's AP1000 at the Sanmen site in China's eastern Zhejiang province had achieved its first sustained nuclear fission reaction. With this key milestone, Sanmen Unit 1 has moved yet one step closer to grid connection and eventual commercial operation, which is still predicted for the end of this year. The AP1000 at Sanmen was designed by Westinghouse Electric Company and is majority-owned by the China National Nuclear Corporation (CNNC). The holder of the technology and primary project operator on the Chinese side is the State Nuclear Power Technology Corporation (SNPTC), which is a business unit within the massive Chinese electricity utility State Power Investment Corporation (SPIC). The Sanmen Unit 1 plant began construction in 2009 and is more than 4 years delayed relative to the original construction schedule. As a new reactor design with numerous first-of-a-kind technology applications, the Sanmen 1 AP1000 encountered numerous challenges to its original construction timeline, including technology re-designs, faulty equipment manufacturing, hiccups in construction project management, and lengthy regulator-mandated safety reviews. Nicobar anticipates that no less than 6-10 additional Chinese reactors will begin construction in the months following the successful commercial operation of Sanmen 1, including AP1000 sites at Lufeng and Xudapu, the CAP1400s at Shidaowan, and potentially more AP1000s at Sanmen and Haiyang Phase II. 

First Fuel Load at Haiyang I

A day prior, on June 21, 2018, Chinese media also reported that the AP1000 at Haiyang Unit 1 in Shandong Province had received authorization from the NNSA to load fuel for the first time. Haiyang Unit 1 will become the second Chinese AP1000 reactor to load fuel, after Sanmen Unit 1. Haiyang Unit 1 will become the first operating nuclear asset that is majority-owned by the State Nuclear Power Technology Corporation (as opposed to simply being the technology license holder and operator). It is anticipated that the Haiyang 1 operation will provide a much-needed injection of operating cash for SNPTC, which has seen its key asset's completion delayed for 4+ years. An aggressive timeline for completion would mirror that of Sanmen 1, and see Haiyang 1 entering commercial operation by Q4 2018 or Q1 2019 at the latest. Haiyang 1 poured first concrete in September 2009.

Nuclear News Weekly Roundup - 06/11 - 06/15

Primary Beam of Karachi Unit 3’s Ring Crane Installed

On the afternoon of June 8th, the primary beam of Karachi Unit 3’s ring crane was hoisted up and successfully lowered on the ring rail at the top of the containment building. All components of the primary beam are assembled on the ground prior to and the beam is installed as one piece. The installation technology is the same used for K2 ring crane’s primary beam. 

 

Tianwan Unit 5’s Containment Dome Attached

On June 10th, Tianwan Unit 5’s containment dome is successfully installed.

 

Tianwan Unit 3’s Tariff Released: 0.401 Yuan/kWh

The Jiangsu Province Bureau of Price recently announced that based on relevant NDRC policies, the ad hoc tariff for electricity generated by Tianwan Unit 3 is 0.401 Yuan/kWh, lower than the 0.43 national benchmark. According to the 2013 NDRC policy, the national benchmark price for nuclear power generated electricity is 0.43 Yuan/kWh. In those provinces where the coal powered benchmark prices are lower than 0.43 Yuan, nuclear tariff should adjust to the coal prices; in provinces where local coal powered electricity prices are higher than the nuclear benchmark, demonstration nuclear projects may raise their tariffs upon NDRC assessment. Tianwan Unit 3 uses a VVER V428M reactor design, which is Gen II plus technology. Thus, the unit can’t be a demonstration project.

 

Shielding Castle of Fuqing Units 5 & 6’s RCP Hydraulic Components Passed Pre-Shipping Inspection

The shielding castle of Fuqing Units 5 & 6’s RCP hydraulic components have recently passed pre-shipping inspection recently. The shielding castle is produced by China Shipbuilding Industry Corporation (CSIC) 719 Institute’s Haiwang Renewable Company and will be shipped to the Fuqing NPP site soon.

 

Progress on 3D Printing Technology for Small Lead-based Reactor Manufacturing

The FDS Fenglin Nuclear Energy Team at the Institute of Nuclear Energy Safety Technology of Chinese Academy of Sciences have recently realized the manufacturing of Small Lead-based Reactor’s integrated tube bundles via 3D printing. The integrated tube bundles is a core component of the Small Lead-based Reactor. It requires sophisticated technology to meet its high requirements for wielding and configuration, given its condensed compact structure.

 

China Building a Nuclear Industry University

On June 15th, Tianjin municipal government and the CNNC singed a framework agreement on building a university dedicated to nuclear industry in Tianjin city. The university is tentatively named as China Nuclear Industry University and it may follow the model of the University of Chinese Academy of Sciences.

 

Nuclear News Weekly Roundup - 06/04 - 06/08

CNNC Signs Multiple Contracts with Russia’s Rosatom for Gen III & IV Reactor Technology Cooperation

On June 8th, one day before the Shanghai Cooperation Organization Summit in Qingdao, state-owned nuclear utilities CNNC and Rosatom Corp. signed three framework agreements: the Tianwan NPP Unit 7/8 Framework Contract, the Xudapu NPP Framework Contract, and the China Demonstration Fast Reactor Equipment Supply and Service Procurement Framework Contract. According to CNNC’s announcement, Tianwan Units 7 & 8, as well as Xudapu Units 3 & 4 (phase II), will use Russian VVER-1200 reactor technology. The two parties will also cooperate on equipment and services for the China Demonstration Fast Reactor (CDFR) currently under construction at Xiapu as of December 2017.

Xudapu Unit 1 & 2 (Phase I) were approved to use the AP1000 design, and prior to Friday’s announcement it was widely assumed that Phase II would also feature AP1000 reactors. This decision represents an unprecedented break with convention to site two different Gen III design trees for construction at a single site.  The two corporations signed the contracts at the Great Hall of the People in Beijing, witnessed by Chinese President Xi Jinping and Russian President Putin.

 

Fangchenggang Unit 3’s Containment Dome Attached

On May 23rd, the containment dome of Fangchenggang Unit 3, CGN’s HPR000 demonstration project, was successfully installed. The milestone indicates that Unit 3’s civil construction phase has completed and the main installation phase has begun. The containment dome has a height of 13 meters, diameter of 45 meters and weighs more than 220 tons.

 

Key Progress on the National S&T Major Nuclear Project CAP1400 Demonstration Project

On April 26th, the “CAP1400 passive containment cooling system performance study and research” project passed NEA inspection. As a key safety and design feature of the CAP1400 reactor type, the passive containment cooling system uses gravity-driven injection, interior steam condensation and exterior water film evaporation to remove post-accident heat and protect the integrity of the containment. The project was issued by the NEA in 2011 as a joint project between SNERDI, SNPTC’s Huaqing Nuclear Technology Development Company, and Shanghai Jiao Tong University.

On June 1st, the “CAP1400 NPP digital instrumentation and control (I&C) system prototype development” project passed the NEA inspection, signifying the success of a NPP digital control system with proprietary intellectual property. A digital control system serves as the nervous system of a NPP and is key to safe and stable operation of the plant. NPP digital control technology is seen as one of the final missing pieces to reach complete localization of Gen III technology. The CAP1400 NPP digital I&C system prototype development project was established in 2014, issued by the NEA. SNPTC’s State Nuclear Power Automation System Engineering Company led the project. Other contributors include SERDI and State Nuclear Power Engineering Company.

 

 

Nuclear News Weekly Roundup - 05/28 - 06/01

Progress on Tianwan Unit 6’s Equipment Production and Civil Construction

On May 25th, Tianwan Unit 6’s pressure vessel passed hydraulic testing and is one step closer to final delivery. Designed and procured by Nuclear Power Institute of China (NPIC), the pressure vessel is manufactured by China First Heavy Industries (CFHI). Representatives from the NNSA, Jiangsu Nuclear Power Company, NPIC, and CFHI witnessed the success of the hydraulic test.

On May 29th, Unit 6 finished pouring concrete for the CI turbine operating floor. It paves the way for subsequent work on equipment installation. The operating floor has a length of 68 meters and a width of 17.8 meters and the primary beam is 4-meter thick. A volume of 1911 m³concrete was poured in 19 hours and 37 minutes. Tianwan Units 5 & 6 are the last two Gen II (M310) units under construction in China.

Karachi Unit 3’s Pressure Vessel Shipped to Pakistan  

On May 22nd, the pressure vessel of Karachi Unit 3, the second HPR1000 export to Pakistan, passed the pre-shipping inspection at China First Heavy Industries Company (CFHI) and was shipped to site. The pressure vessel is a proprietary design of NPIC that was ordered by the newly-established CNNC Supply Chain Management Company, and manufactured by CFHI.

As the only non-replaceable piece of primary equipment within a NPP, the design & manufacture of the RPV represents a significant technological challenge. The self-developed pressure vessel for HPR1000 has many innovative design features, which include improvements for safety and reliability. It has only been 9 months after shipping of the pressure vessel for Karachi Unit 2 in August 2018, indicating a progress of China nuclear industry to manufacture nuclear equipment in scale.

 

Taishan Unit 1 Reaching First Criticality

The NNSA organized an inspection of Taishan NPP’s preparatory work for Unit 1’s first criticality from May 22nd to 25th. The NNSA concluded that Taishan Unit 1 satisfied the requirements to release hold point for first criticality and proceed with reactor start up.

 

The Nuclear Power Institute of China (NPIC) Obtained HAF 601 Certificate

NPIC obtained its first HAF 601 manufacturing certificate for small reactor once-through steam generators (OTSG). NPIC now holds a relatively comprehensive certification scope and is well-positioned for the design and manufacture of civil nuclear safety machinery, electrical equipment, as well as the inspection of civil nuclear safety equipment.

 

NPIC and CNNC’s SUFA Valve Company Sign NPP Pilot Safety Valve Joint R&D Agreement

The Vice Director of the Nuclear Power Institute and Vice President of the Suzhou Valve Company recently formally signed a joint development agreement for the development of new cutting-edge safety valve technology for nuclear power plants. The signing of the agreement marks an important step forward in the cooperation between the two companies.

 

Taihai Manoir and SNERDI Work Together to Develop Super Austenitic Stainless Steel Pipes and Fittings     

On the evening of May 31st, Taihai Manoir Nuclear Equipment Company announced that the company recently received a contract for a research sub-task of a Key National Project. The contract was awarded by the Shanghai Nuclear Engineering Research and Design Institute (SNERDI) for “the localization of super austenitic stainless steel pipes and fittings for sea water intake systems of nuclear power plants.”

 

 

Nuclear News Weekly Roundup - 05/21 - 05/25

Yangjiang Unit 5 Connected to the Grid  

On May 23rd Yangjiang Unit 5, an ACPR1000 design, was connected to the grid, becoming this year’s first under-construction unit to hit this milestone in China. Yangjiang NPP is the largest nuclear power project in China. According to CGN, Unit 5 is also the first domestic reactor design to employ major features of Gen III technology*, using CGN’s self-developed Hemu (harmony) digital control system (DCS). Yangjiang Unit 5 poured its first concrete in September 2013 and it is now CGN’s 21st operational nuclear power unit.

 

*Nicobar Note: the ACPR1000 is usually regarded as a Gen II + reactor design, and is the basis for CGN’s HPR1000 Gen III design under construction at Fangchenggang Units 3&4.

 

Fangchenggang Unit 3’s Containment Dome Attached

On May 23rd, CGN’s HPR1000 demonstration project, Fangchenggang Unit 3, had its containment dome attached 8 days ahead of schedule, which now advances the project to its installation phase. The dome has a diameter of 45 meters and a height of 13.6 meters. It consists of 70 wall panels and weighs more than 220 tons. It is a great challenge to hoist the dome as a whole and attach it, 63 meters above ground, to the containment building. “We employed innovative 3-D modelling technology and made a sand-table model to identify potential challenges and work out respective solutions, so we can make sure the attachment would be a success on the first try” said Guo Zonglin, Vice GM of China Nuclear Power Engineering Company (CNPEC) and Chief Director of the Fangchenggang HPR1000 demonstration project.

Fangchenggang Unit 3 uses CGN’s HPR1000 reactor design, a Gen III technology that China has full proprietary intellectual property of. Almost 90% of its equipment is locally manufactured, and the design will be the representative “going out” nuclear technology to be exported. According to CGN and EDF’s cooperation agreement signed in 2015, the Bradwell B Project in the U.K. will employ the HPR1000 reactor design and use Fangchenggang Unit 3 as a reference model. Currently, the HPR1000 reactor design is in Phase II of the Generic Design Assessment conducted by British nuclear regulatory authorities and is projected to enter Phase III by the end of 2018.      

 

Nuclear Power Institute of China Developed the First Reactor Core Measurement System for the HPR1000

On May 20th, Deputy Director of Nuclear Power Institute of China (NPIC), Wu Lin, announced that the Hengxin TM, the self-developed reactor core measurement system for world’s first HPR1000, had its first batch of equipment packed for shipment. It took NPIC ten years to develop a reactor core measurement system with proprietary intellectual property. The equipment will be used at Fuqing Unit 5 to measure its real-time neutron flux rate and coolant temperature at fuel assembly outlet, among other indicators.   

 

Harbin Electric Power Equipment Company (HEPEC) Becomes Westinghouse’s First and Only Qualified Supplier in China

On May 23rd, an issuance ceremony was held at Harbin Electric Power Equipment Company (Qinhuangdao city) where it received its Certificate of Qualified Supplier from Westinghouse Electric. Mr. Joni Falascino and Mr. Jan Dudiak, Westinghouse Electric’s Senior VP and Chief Procurement Officer, respectively, presented the certificate (serial number WEC-00000001) to HEPEC.

 

SPIC and China Energy Engineering Corporation Signed Framework Agreement on Strategic Cooperation

On May 22nd, State Power Investment Corporation (SPIC) and China Energy Engineering Corporation (CEEC) signed a framework agreement on strategic cooperation. The two corporations will work together in the future on nuclear power, engineering construction and ancillary services, consulting and other services, capital investment, technology and human resources, international projects, information sharing, etc.  

 

Primary Helium Fan of Huaneng’s HTGR at Shidaowan Passed Pre-Shipment Inspection

On May 17th, the primary helium fan of the world’s first High Temperature Gas-Cooled Reactor passed the pre-shipment inspection at Jiamusi Electric Machine Company, a subsidiary of Harbin Electric Corporation. The inspection procedure contained many items, including an aerodynamics test, a 100-hour stable state test, an electric motor performance test, etc. All test results satisfy passing standards and the product is ready to be shipped to the Shidaowan site in Shandong Province.

 

HAF604 Blotter: Q1 2018

HAF604 certification and registration activity from the First Quarter of 2018, retrieved and translated from the Chinese National Nuclear Safety Administration (NNSA). 

1/17/2018: 

HAF604 Certificate Adjustments: 

AB Sandvik Materials Technology: Changed its legal representative from Petra Einarsson to Göran Björkman
BÖHLER Edelstahl GmbH & Co KG: Changed the name on its certificate from BÖHLER Edelstahl GmbH & Co KG to voestalpine BÖHLER Edelstahl GmbH & Co KG

2/24/2018

HAF604 New Certificates

Benning Elektrotechnik und Elektronik GmbH & Co KG: Certified for the design and manufacture of chargers, inverters and uninterruptible power supplies. 
EnerSys S.A.R.L.: Certified for the Design and manufacture of storage batteries, and lead acid battery arrays. 

HAF604 Scope Adjustments: 

voestalpine BOHLER Edelstahl GmbH & Co KG: Added castings for vessels to its certification scope
Salzgitter Mannesmann Stainless Tubes Italia SRL: Added manufacture of heat exchanger tubes to its certification scope
Westinghouse Electric Company, LLC: Added design and manufacture of AC medium voltage switchgear cabinets, AC low voltage switchgear cabinets, DC switchgear cabinets, electrical boards, platforms, screens and boxes

HAF604 Re-Certifications: 

Intercontrole: For performance of Ultrasonic Testing and Eddy Current Testing on the RPV, SG, and pressurizer expansion tubing weld seams
Patriot Forge: Castings for valves and pumps, vessels and supports
SPX Flow US, LLC: For design and manufacture of explosion valves

3/21/2018

HAF604 Certificate Adjustments:

New NP SAS: Changed name to FRAMATOME SAS
KSB Aktiengesellschaft: Changed name to KSB SE & Co. KGaA and changed legal representative from Peter Buthmann, Matthias Schmitz, Ralf Kannefass, Stephan Bross to Stephan Timmermann, Matthias Schmitz, Ralf Kannefass, Stephan Bross. 

4/3/2018

HAF604 Certificate Adjustments: 

New NP GmbH: Changed name to FRAMATOME GmbH
Fisher Controls International LLC: Changed legal representative from Chad Engle to Tim Parrie

4/4/2018

HAF604 New Certificates: 

AEG Power Solutions GmbH: For the design and manufacture of chargers, inverters and uninterruptible power supplies

HAF604 Scope Adjustments: 

Swagelok Company: Added design and manufacture of pipe reducers and pipe instrumentation to its certification scope

HAF604 Re-Certifications: 

Metaltek International, Inc.: For castings for valves, valves bodies, and valve covers
JSC "Central Design Bureau of Machine Building": For design and manufacture of centrifigual pumps, shell-type heat exchangers and equipment supports
Scot Forge Company: For castings for vessels, CRDM, pumps and valves, and pump covers

Nuclear News Weekly Roundup - 05/14 - 05/18

Progress on HPR1000 Demonstration Project: All Key Equipment of Fuqing Unit 5’s Primary Coolant System Installed; Other Equipment for Unit 5&6 Shipped

On May 10th, Fuqing Unit 5’s coolant pump was shipped from Harbin Electric. The coolant pump underwent a teardown inspection and was packed up after successfully completing the full-flow test on March 26th, 2018. Six days later, on May 16th, Fuqing Unit 5’s pressurizer, the last piece of its primary equipment in the nuclear island, was also successfully installed following the steam generator and pressure vessel. Meanwhile, 4 high-pressure heaters for both Unit 5 & 6 were also shipped from Harbin Electric.

 

Primary Piping Welding Started for Hongyanhe Unit 5

On May 11th, Hongyanhe Unit 5’s first seam weld hold-point on primary piping, referred to as 1C4, was released by the NNSA. Welding of the piping began at 3:46 pm. Representatives from CNPEC, Liaoning Nuclear Power Company, and China Nuclear Industry 23 Construction Company were present to witness the milestone, which signifies that Hongyanhe Unit 5 has entered the phase of primary system installation.

 

Haiyang Unit 2 Finished the Non-Nuclear Start-up Test of the CI Steam Turbine

On May 10th, Haiyang Unit 2’s CI steam turbine was sped up to 1500 rpm during pre-fuel load commissioning testing. All device readings are reported to have passed the qualification threshold. The steam turbine was manufactured by Shandong Electric Power Construction First Engineering Company (SEPCO1).

 

China Nuclear Power Now Included into the MSCI Emerging Markets Index

Morgan Stanley Capital International (MSCI) just announced the half-year index adjustments on how Chinese A shares will be calculated. China National Nuclear Power Company (CNNP), subsidiary of the CNNC and its public branch listed in Shanghai Stock Exchange, and China Nuclear Engineering Group Corporation (CNEC) will be both included among other 234 Chinese A-share stocks. It is the first time that Chinese nuclear firms are included in MSCI’s Emerging Markets Index. The adjustment will go into effect on May 31st, 2018.

 

Nuclear Grade Zirconium and Hafnium Sponge Successfully Localized

The CNNC 272 Uranium Industry LLC has recently manufactured nuclear grade zirconium and hafnium sponge successfully, reaching another milestone for localization of nuclear fuel element containment vessel production. Zirconium and Hafnium have similar physical and chemical properties and it is very difficult to separate them from each other. However, their purified alloys are both necessities for nuclear fuel component production. Only a few countries in the world, like France, possesses the technology. China currently relies heavily on the import of these elements for use in fuel production.

 

Vice GM of Lufeng Nuclear Power Company Visited SEC-KSB for Wet-Wound Pump Development Progress

On May 11th, Bian Shuming, Vice General Manager of Lufeng Nuclear Power Company, accompanied by procurement center staff of the State Nuclear Power Engineering Company (SNPEC), visited Shanghai Electric-KSB. Bian introduced the current status of the Lufeng NPP project and learned about the progress of SEC-KSB’s wet-wound RCP development project. Both parties discussed the details of the testing of the CAP1400 prototype pump and the status of the design of the CAP1000 RCP.

 

Equipment Passed Pre-shipping Evaluation, Shipped to Tianwan NPP

Tianwan Unit 5’s fuel transfer device and Unit 6’s refueling machine electric control system passed pre-shipping evaluation and were shipped to site. The equipment is produced by CNNC’s China Nuclear Control System Engineering Company. An expert panel consisting of engineers from Xi’an Nuclear Equipment Company (XNE), Jiangsu Nuclear Power Company (JNPC), and China Nuclear Power Engineering Company (CNPE) examined all relevant inspection points and decided that the equipment was qualified for shipping.  

Nuclear News Weekly Roundup - 05/07 - 05/11

China (Shanghai) Experimental Free Trade Integrated Development Platform Established

On the afternoon of May 9th, China’s first integrated central-local development platform – the China (Shanghai) Experimental Free Trade Zone’s integrated central-local development platform establishing ceremony was held at Shanghai Expo Central SOE headquarters base. The platform is jointly prepared by Shanghai Municipal Commission of Economy and Informatization and Pudong New Area Government and the future CNNC Shanghai headquarters will also locate in this area.

 

Taihai Manoir Nuclear Equipment Co. Ltd Reached Deal with Taihai Group to Purchase 100% of the Shares of Manoir Industries

Taihai Manoir Nuclear Equipment Co. Ltd announced on the evening of May 6th that it has signed a framework agreement with Yantai Taihai Group to purchase 100% of the shares of Manoir Industries. Taihai Manoir was formed in 2013 when Yantai Taihai Group acquired the nuclear, petrochemical and specialty business units of Manoir Industries. Both parties will make the final share trade plan upon further detailed communication on due diligence, auditing, evaluation, and discussion with regulating authorities.

 

“HPR1000 Reactor By-pass System Configuration Study” Evaluation Conference Held in Xi’an  

On April 27th, the evaluation conference of the “HPR1000 Reactor By-pass System Configuration Study” was held in Xi’an. The project was conducted by China Energy Engineering Corporation’s China Power Engineering Consulting Group (CPECC). Experts and representatives from the CPECC headquarter as well as the Electric Power Planning & Engineering Institute (EPPEI), EPECC’s six major subsidiary institutes and other organizations attended the conference. The study project analyzed the function of the bypass system and designed a configuration plan for it, including the allocation and layout of bypass valves and a design plan for the desuperheating water system, etc. The expert panel decided that the study project met its proposed requirements and is of direct significance to the subsequent work on the HPR1000 reactor type’s by-pass system. The project passed the evaluations.

 

Design and Testing Plan of the Test Platform for Equipment Usability in CAP1400 Severe Accident Hydrogen Explosion Environment Passed Examination

The design and testing plan of the test platform for equipment usability in CAP1400 severe accident hydrogen explosion environment, a CAP1400 Key National Project’s subsector project, recently passed its expert examination. Zhongchuan Heavy Industry’s No. 718 Institute developed the plan, which passed the evaluation. The evaluating panel consists of experts from the Ministry of Ecology and Environment’s Nuclear and Radiation Safety Center, the State Power Investment Corporation (SPIC), the State Nuclear Power Technology Company (SNPTC), Shanghai Jiao Tong University, Xi’an Jiaotong University, and SNERDI. 

 

Tianwan Unit 4 Finished Hot Testing, Preparing for Fuel-loading

At 23:15, May 7th, Tianwan Unit 4’s primary coolant system cycled down to 70 degrees Celsius, coming down from hot testing. It signifies that Tianwan Unit 4’s 42-day hot testing was successfully completed and is now in the phase of pre-fuel loading preparation. Tianwan Unit 4 is a VVER-1000 design that began pouring concrete in September 2013. Its sister unit at Tianwan 3 was connected to the grid in March, 2018.

 

Nuclear News Weekly Roundup - 04/30 - 05/04

Tianwan Unit 6’s Containment Dome Attached 26 Days Ahead of Schedule

On the afternoon of May 5th, Tianwan Unit 6’s containment dome was attached to the reactor building, 26 days ahead of schedule. It has taken field workers just 20 months since FCD. Next, key equipment inside the nuclear island will be installed. The reactor model at Tianwan 6 is a Gen II plus Chinese-designed CPR1000.

 

China Energy Research Society’s Nuclear Specialized Committee Formed in Suzhou

On May 4th, an establishment conference for the newly formed Nuclear Specialized Committee of the China Energy Research Society (CERS) was held in Suzhou, which was also the opening ceremony of the Future of Nuclear Power Development forum. Suzhou Nuclear Power Research Institute’s (SNPI) secretariat will be the primary supporting organization of the committee, which is aimed at becoming the most influential academic organization in China nuclear policy and technology research.

 

Karachi Unit 2’s Reactor Internals Shipped from Shanghai

On May 2nd, the reactor internals for Karachi Unit 2 (K2), China’s first HPR1000 export to Pakistan, were shipped from Shanghai Electric’s No.1 Machine Tools Plant. It was the second batch of HPR1000 reactor internals delivered from Shanghai Electric since April 10th, when those of Fuqing Unit 5 were shipped.

 

Steam Generator of Hongyanhe Unit 5 Successfully Installed

Hongyanhe Unit 5’s steam generator was shipped to site on April 23rd and was successfully installed last week. The steam generator has a length of 21 meters and a diameter of 4.4 meters. It weighs 336 tons. 

 

 

Nuclear News Weekly Roundup - 04/23 - 04/29

Sanmen Unit 1 Finished Its First Fuel-loading

On April 25th, the long-lasting uncertainty around the AP1000 at Sanmen was brought to an end: the NNSA decided that Sanmen Unit 1 is qualified in all aspects of design, equipment, construction and installation, commissioning, pre-operation preparation and can proceed to fuel-loading. Mr. Liu Hua, Director of the NNSA and Deputy Minister of the Ministry of Ecology and Environment (formerly the MEP), issued approval for Sanmen Nuclear Power Company to begin loading first fuel for Sanmen Unit 1. At 7:46 p.m., the first fuel bundle was carefully loaded, and on the afternoon of April 29th, the last of the 157 fuel bundles were placed in the reactor core and Sanmen Unit 1’s first fuel-loading was completed successfully.

 The milestone represents one of the key finals steps towards grid connection for the world’s first AP1000 unit, and by extension one of China’s final hurdles to releasing its next wave of pre-approved Gen III projects, opening the path for a period rapid growth in China nuclear.

 *Read Nicobar analysis for more detailed information

 

Yangjiang Unit 5 Received Approval for Fuel-loading

On April 17th, 2018, Yangjiang Unit 5 received its approval for the first fuel-load from the NNSA. Yangjiang Unit 5 poured its first concrete on September 18th, 2013. Its reactor design is ACPR1000+, CGN’s Gen II plus technology. Yangjiang Units 1-4 started commercial operation on March 25th, 2014; June 5th, 2015; January 1st, 2016; and March 15th, 2017 respectively.

Fangchenggang Unit 5’s All 6 Safety Injection Tanks Shipped to Site  

On April 18th, the last of Fangchenggang Unit 5’s 6 safety injection tanks was shipped from Dongfang Industrial Boiler Group. The safety injection tank is an important part of the Safety Injection System. The tank contains boric acid maintained in reserve during normal operation, with its upper part filled with pressurized nitrogen. When the pressure in the primary coolant system drops below that of the safety injection tanks, boric acid will be automatically released into the system, driven by the pressure differential with the pressurized nitrogen, in order to arrest the nuclear reaction and assist in cooling the reactor core.

Hongyanhe Unit 5’s Steam Generator Shipped to Site

On April 23rd, Hongyanhe Unit 5’s first steam generator was shipped to site from China First Heavy Industries (DFHI) Dalian Nuclear Power Petrochemical Company in Dalian. The steam generator has a height of almost 21 meters and a weight of more than 300 tons. It arrived the NPP the same day. Hongyanhe Unit 5 has two more steam generators which will also be manufactured by DFHI. As most of the nuclear island’s key equipment is now delivered on site, Unit 5 is entering the apex of its installation period.

 

Progress of Karachi Unit 3: Ring Crane Mounted and Rotor Manufactured

On the morning of April 25th, local time, Karachi Unit 3, China’s HPR1000 export to Pakistan, had its ring crane girder and rail mounted. Meanwhile, its welded rotor, the largest nuclear power welded rotor in the world, has been recently finished processing at Shanghai Electric Lingang Heavy Machinery Company. The rotor will be shipped from Shanghai to Pakistan soon.

Sanmen Unit 1 Fuel-loading a Key Win for SNPTC and WEC, but Future for AP1000 Still Unclear

Two days ago, on April 25th, the long-lasting uncertainty surrounding China’s first AP1000 at the Sanmen NPP site was brought to an end: the NNSA ultimately decided that Sanmen Unit 1 is qualified in all aspects of design, equipment, construction and installation, commissioning, pre-operation preparation and can proceed to fuel-loading. Mr. Liu Hua, Director of the NNSA and Deputy Minister of the Ministry of Ecology and Environment (former MEP), issued Sanmen Nuclear Power Company an approval for Sanmen Unit 1 to load its first fuel. At 7:46 p.m., the first fuel bundle was carefully loaded in the reactor core, one of the key finals steps to grid connection for the world’s first AP1000 unit. The milestone also indicates that China’s last obstacle to completing its pre-approved Gen III projects has been overcome, potentially opening the path for a period of rapid growth in China nuclear. By Nicobar’s estimates, there are at least 10 reactor units awaiting FCD currently bottle-necked behind the first AP1000, and many more to follow. Still unclear, however, is the durability of the role the AP1000 will be playing in the years to come.

The good news for Sanmen came directly on the heels of the announcement that the EPR at Taishan Unit 1 had received the approval from the NNSA to start fuel-loading and became the first Gen III unit in China to load its fuel back on April 10. Despite being the fastest constructed EPR unit around the world (it gained recognition as the World’s First EPR Unit in January 2018 during French President Macron’s state visit to China), many nuclear industry personnel had begun to associate the China EPR with the same kind of unending construction cycle affecting the Finnish and French deployments. By contrast, the world’s first AP1000 at Sanmen had always been the focus of attention and had generally been regarded by many to have the best chance to become the first operating Gen III unit in China. It was certainly a point of surprise in the industry that the trouble-plagued French design ended up receiving approval for fuel loading before Sanmen.  

Westinghouse and its Chinese partners had claimed that Sanmen Unit 1 has been technologically ready for fuel-loading since late 2017. In spite of those assertions, Sanmen Unit 1 had entered 2018 (its tenth year of construction) without its fuel-load approval (five years behind its original schedule). Initiating this key pre-cursor step to grid connection had been postponed these last six months by a new round of regulator inquiries concerning the reactor coolant pump (RCP). At the end of 2017, some Chinese industry insiders believed that further evaluation, specifically a tear-down examination, was necessary for the uniquely-designed RCP. Other commentators bluntly challenged the the decision-making of the Chinese nuclear regulatory authorities, arguing that a hasty fuel-loading approval would constitute a serious dereliction of duty. These concerns likely affected the NNSA’s decision to assume a cautious posture and prompted the further rounds of safety testing that have apparently finally concluded successfully.

The repeated delay of Sanmen Unit 1 undoubtedly also impacted the development and national strategy of the Chinese nuclear power industry. Policy makers had placed high hopes on the AP1000 and a series of future Gen III units derived from the reactor design had been planned for years. As construction became increasingly bogged down over the last decade, Chinese industry planners shifted their focus to other technology types, especially the self-developed HPR1000/Hualong One. For instance, it was officially announced last month that the merged design of the HPR1000 will be built at CNNC’s Zhangzhou project and CGN’s Taipingling/Huizhou project, replacing the originally planned AP1000s at these sites.  Other AP1000 projects have been cancelled outright with no replacement technology stated yet.

As China is determined to increase the share of nuclear power in its energy mix and has a stated objective of taking the lead in international nuclear power market, the slowdown in recent years will need to be made up somehow. The China Nuclear Energy Association (CNEA) released its publication Blue Book of Nuclear Energy – the Report on the development of China’s Nuclear Energy (2018) and the Report on China Gen III Nuclear Power Development Strategic Value Research on April 23rd of this year, emphasizing that nuclear power is currently underdeveloped and China now should have strong advantages in Gen III technology. Additionally, previous estimates and objectives have been revised to account for the slowdown in the deployment schedule According to the reports, as China is finally able to enter the scale deployment phase of its planned Gen III units and a new strategic development plan should be plotted towards 2035. In the very near future, China should witness 6-8 FCDs of Gen III units (this matches Nicobar estimates) and by 2030, nuclear power should reach 10% in the energy mix as opposed to the current 3.94%. By Nicobar estimates, this will require a 6-8 FCD per year deployment schedule over the next few years.

For advocates of Chinese nuclear power development, the current situation presents a logistic challenge to meeting these goals. Even with the fuel load for Sanmen Unit 1 starting now, the earliest that unit can be connected to the grid will be Q3-4 2018, as confirmed by a CNNC spokesperson in March 2018. Furthermore, the HPR1000 demonstration projects in Fuqing and Fangchenggang will not begin commercial operation until 2020 or 2021, at the earliest. Thus, if China sticks to its demonstration plant deployment model, it will only be possible to begin building more AP1000s in 2019, and more HPR1000s in 2021, which will likely make the 6-8 FCD/year target very difficult to meet, with the 2030 target nigh-impossible. This logistical problem has not gone unnoticed within the industry. Last month, during the 15th Nuclear Industry China exhibition in Beijing, Mr. Zhao Chengkun, Deputy Director of the CNEA and former Director of the NNSA, called for more aggressive deployments. Mr. Zhao argued that the merged HPR1000 design is now ready for immediate new FCDs due to its safety features and advantages versus other international Gen III technologies. He pointed out that stimulating the developing of plants would have positive effects for manufacturers whose equipment currently lies idle, and that aggressive nuclear power growth would also serve to prevent ‘brain drain’ in the industry. In essence, his position is that it is unnecessary and disadvantageous to wait for the 2021 grid connection of the demonstration HPR1000 projects in Fuqing & Fangchenggang. Obviously following this line of thinking cannot mean good things for the AP1000.

Whether the good news for Sanmen Unit 1 means the AP1000 design has secured its lifeline for at least a few more years of deployments, or whether the advocates for immediately deploying more HPR1000s will get their way remains to be seen. The Chinese regulator has walked a fine line in the past to balance the needs of an aggressive national development blueprint and a conservative proof-of-concept deployment model. Conservatism clearly won out when it came to approval for Sanmen’s fuel load. If this conservative posture continues going forward, then the AP1000 is likely to enjoy several more years of domestic deployments. If the more aggressive model advocated by Mr. Zhao gains favor, however, the future of the AP1000 for China deployments could still be in serious trouble, in spite of the good news this week from Sanmen.

Nuclear News Weekly Roundup - 04/16 - 04/20

The CAP1400 Control Rod Drive Mechanism (CRDM) Development Program, a Nuclear Power Key National Project, Passed Acceptance Inspection

From April 9th to 10th The NEA Nuclear Power Department held an expert acceptance review of the CAP1400 CRDM development program’s work progress and financial accounting. The CRDM development project is a sub-program of the Large Advanced Pressurized Water Reactor and HTGR Key National Project. Shanghai Electric’s No.1 Machine Tools Plant led the program and Shanghai Power Equipment Research Institute undertook one of the primary subtasks of the program. The conference expert panel verified the CRDM prototype and relevant materials and concluded that the program passed the acceptance inspection.

 

CNNC Held Seminar with NPPD in Beijing, Completed the Contract on Iran’s Arak Heavy-water Reactor Renovation

On April 11th, a conference titled “Strengthening Sino-Iranian Civil Nuclear Cooperation, Advance Implementation of the JCPOA” was held in Beijing. The Arak heavy-water reactor renovation was a major focus of the event and is a key part of the Joint Comprehensive Plan of Action (JCPOA, a.k.a. the Iran nuclear deal). CNNC discussed the modification plan it developed and announced that all the auxiliary consulting services had been provided and completed according to the contract. In April 2017, the China Institute of Atomic Energy (CIAE), China Nuclear Energy Industry Corporation (CNEIC), and Nuclear Power Production and Development Company of Iran (NPPD) initialed their first commercial contract to redesign the Arak heavy-water reactor in Beijing,

 

Taipingling/Huizhou NPP Announced Bid Winners of the Civil Construction Projects of Its Nuclear Islands

China Construction Second Engineering Bureau Company and China Nuclear Industry 24th Construction Company won the bid for Taipingling/Huizhou NPP’s Unit 1&2 NI civil construction projects. Their respective bidding prices were CNY 2.37 billion and CNY 2.58billion.

 

The Standardization Implementation Program for the HPR1000 National S&T Major Project Initiated

On the afternoon of April 13th, the National Energy Administration (NEA), the Standardization Administration of China (SAC), and the NNSA jointly released the “HPR1000 National S&T Major Project Standardization Implementation Program” in Beijing, with the goal of building a comprehensive system of standards covering the full life-cycle of the HPR1000 reactor design. The plan intends to apply these standards across all the HRP1000 units built in and outside China over the next 4 years.

 

First Auxiliary Feedwater Pump for Karachi Unit 2, China’s First HPR1000 Export, Completed Pre-shipping Testing

On April 18th, the first auxiliary feedwater pneumatic pump for Karachi Unit 2, China’s first HPR1000 export to Pakistan, completed the pre-shipping testing. The testing was conducted under the oversight of Karachi NPP and Pakistan Nuclear Regulatory Authority (PNRA) representatives. The auxiliary feedwater pneumatic pump was developed by Shanghai Apollo Machinery Company. It is the first 100% self-designed, manufactured, and qualified safety-class pump product in China.

 

The First Conventional Island (CI) Turbine Low-pressure Rotors for Fuqing Unit 5 Successfully Developed & Shipped to Site

On the morning of April 18th, the “heart” of Fuqing Unit 5’s CI turbine, two low-pressure rotors weighing 280 tons respectively, were shipped from Dongfang Turbine Company’s plant in Deyang city, Sichuan Province. The shipment of the rotors signifies that the development of HPR1000’s first CI turbine’s primary modules is now complete, and Dongfang Turbine Company now possesses full capabilities of independently developing CI turbines for HPR1000s. 

 

Nuclear News Weekly Roundup - 04/09 - 04/13

Taishan Unit 1 Started Fuel-loading

On the afternoon of April 10th, Liu Hua, Director of the NNSA and Deputy Minister of the Ministry of Ecology and Environment (former MEP), issued Taishan Nuclear Power Joint Venture Company an approval for Taishan Unit 1 to load fuel for the first time. The MEE’s South China Station of Nuclear and Radiation Safety Inspection verified that Taishan Unit 1 was qualified to begin fuel-loading. Field engineers on-site began to load the first fuel assembly at 20:18 that evening. Taishan Unit 1 was recognized as the World’s First EPR Unit in January 2018 when French President Macron paid a state visit to China and it is now the first Gen III unit in China to start fuel-loading, overtaking the AP1000 at Sanmen.

 

Changjiang NPP Advancing the Phase II Extension Project’s Preparation Work

On March 28th, the General Manager of Hainan Nuclear Power Company, Xu Jun, told a journalist that preparation work for Changjiang NPP’s Phase II extension project is advancing smoothly and the project will build two HPR1000 units. Changjiang NPP is located in western Hainan Province and is planned to build 4 units in total. Units 1&2 of the Phase I project had their FCDs on April 25th, 2010 and November 21st, 2010 and were connected to the grid on August 12th, 2016.

 

Fuqing Unit 5’s Reactor Internals Shipped

On April 12th, the reactor internals of Fuqing Unit 5 were shipped from Shanghai Electric’s No.1 Machine Tools Plant. The reactor internals were designed by the Nuclear Power Institute of China (NPIC). The system supports fuel bundles while absorbing neutrons and gamma rays emitted from the core, protecting the external materials from radiation and prolonging the lifespan of the reactor.

 

Nuclear News Weekly Roundup - 03/31 - 04/06

NEA Director Nur Bekri: Promote Nuclear Power Development Safely and Steadily; Solve the Issue of Clean Energy Being Under-dispatched

Mr. Nur Bekri, Director of the National Energy Administration (NEA) and Deputy Director of the National Development and Reform Commission (NDRC), was recently interviewed by the People’s Daily publication regarding the direction and focus of Chinese energy development strategy in the wake of the 19th CCP National Congress. On the topic of nuclear power development, Bekri said that China will promote nuclear power development safely and steadily and make great efforts to solve the issue of clean energy being under-dispatched.

 

Based on public available information, in the past decade, the growth rate of national power demand slowed down each year yet newly installed capacity increased constantly at the rate of over 8% annually. As a result, capacity factors of NPPs nationwide have degraded over the past several years. In 2015 and 2016, average utilization rates of NPPs were 83.3% and 79.55%.

 

 

Zhangzhou and Taipingling (Huizhou) Projects Ready for FCD on Merged HPR1000 Design

Hualong Pressurized Water Reactor Technology Corporation announced during the 15th China International Nuclear Industry Exhibition that the first-ever merged design of HPR1000 will be built at CNNC’s Zhangzhou NPP project and CGN’s Huizhou/Taipingling project. CNNC and CGN representatives said that both Zhangzhou and Huizhou/Taipingling are on schedule for FCDs in 2018 and are waiting for FCD license approval from Chinese government.

 

Hualong pressurized water reactor technology is China’s self-developed Gen III nuclear technology, created through a fusion of CNNC’s ACP1000 design and CGN’s ACPR1000+ design. Among the current HPR1000 demonstration projects under construction, Fuqing Units 5&6 are derived from the CGN design while CNNC’s HRP1000 at Fangchenggang Units 3&4 are developed from the ACP1000 technology. Under the NEA’s guidance, the technology integration plan was initiated in 2013. In 2015, the first round of integration was completed and the demonstration projects at Fuqing and Fangchenggang were approved to start construction. The second round completed in July 2017 and passed NEA evaluation. The merged HPR1000 design is now ready for immediate new build deployments according to Mr. Zhao Chengkun, Deputy Director of CNEA and former Director of NNSA. Mr. Zhao has argued that the HRP1000 design is very safe and has many advantages compared to other international Gen III technologies. Thus, he has mad vocal appeals for immediate FCDs of subsequent HPR1000 projects, saying that it’s unnecessary to wait until the completion and grid connection of the demonstration projects (in Fuqing & Fangchenggang)

 

China has not issued any approval for NPP new builds since late 2016.

  

Major Crane at Fuqing Unit 5’s CIs Completed Load Tests

The 350/60-ton bridge cranes at Fuqing Unit 5’s conventional islands (CIs) completed load tests recently. All CI cranes are available for usage at this point. Completion of load tests paved the way for subsequent installation work. The major crane is the most important hoisting equipment at CIs. It has two bridge cranes and will lift all CIs’ important equipment during the phases of construction, installation, and maintenance.

 

Progress on Development & Manufacturing of Various NPP Components  

Shanghai Electric successfully completed manufacturing of the reactor internals for Fuqing Unit 5, as well as the steam turbine welded rotors for export to the Karachi HPR1000 project; Ningxia Gongxiang Steel Forging Company and Chinese Academy of Sciences’ Institute of Metal Research made technological breakthroughs on development of high pressure cylinder’s castings for Karachi Unit 3; Jiamusi Electric Machine Company of Harbin Electric manufactured China’s first auxiliary generators for residual heat removal pumps.  

 

Timetable for Travelling Wave Reactor (TWR) Development Revealed

CNNC revealed its roadmap for the development of the travelling wave reactor (TWR) during the 15th China International Nuclear Industry Exhibition. According to CNNC, a 300MV demonstration unit will be built around mid-2020s; meanwhile, manufacturing and supply chain of the metallic fuel assemblies will be localized. By 2030, a 600 MW commercial scale unit will be developed and constructed; and by mid-2030s, CNNC will target completion of a scaled-up 1200 MW design for construction.  

Nuclear News Weekly Roundup - 03/26 - 03/30

Gansu Province Will Build the Experiment Platform for a Thorium Molten Salt Reactor Nuclear Energy System (TMSR) in Wuwei City

The Department of Urban and Rural Housing Construction in Gansu Province released Notice on Site-Selection Plan of the TMSR Experiment Platform Program and Notice on Site-Selection Plan of Affiliated Programs of the TMSR Experiment Platform Program on March 27th. The notices are for public opinion collection and will expire on April 2nd. Should they receive no objections, the experiment platform and its affiliated programs will be built in the industry park in Minqin County of Wuwei city of Gansu Province. According to publicly available information, Chinese Academy of Sciences’ Shanghai Institute of Applied Physics as the program owner has filed the site-selection application to the Gansu Provincial Government. TMSR is one of the six Gen IV designs featuring higher inherent safety, less spent fuel, lower proliferation risks, and more economic operations. Gansu Province has abundant mineral resources that the TMSR can use, fitting into Gansu’s current strategy to develop the unconventional energy industry.

 

Tianwan Unit 4 has Started Hot Testing on March 27th

Tianwan Unit 4 began hot testing on March 27th. This lays the foundation for the subsequent major milestones of fuel-loading and eventual realization of commercial operation in 2018.

 

The 15th Nuclear Industry China (NIC) Opened on March 28th in Beijing

On the morning of March 28th, the 15th China International Nuclear Industry Exhibition opened at the China National Convention Center in Beijing. The topic of this year’s NIC was: “Innovation & Cooperation: Nuclear Energy Powering Beautiful Life.”   

 

NPIC has Won the Bid for Xiapu 600MW Fast Reactor Demonstration Project’s Electric Heater

Dongfang Electric (Guangzhou) sent the bid-winning notice to the Nuclear Power Institute of China (NPIC) on March 26th. NPIC won the bid to supply electric heaters to Xiapu’s 600 MW fast reactor demonstration project. The 175 electric heaters are used in the primary and secondary coolant systems and are estimated to be delivered in early 2019.

 

Lanzhou University of Technology has Developed China’s First 600 Bismuth Alloy Canned Motor Pump

China’s first 600  ℃ high-temperature liquid lead-bismuth alloy canned motor pump has been successfully developed. It was designed by Dr. Cheng Xiaorui of Lanzhou University of Technology and manufactured by Dalian Sifang Electric Pump Company. It has now been delivered to the Chinese Academy of Sciences’ Institute of Modern Physics and is under test operations. It represents another technology breakthrough in China.

 

Fuqing Unit 5’s RCP has Finished Its Full-flow Test

Fuqing Unit 5’s RCP has finished its full-flow test, signaling that the development of the RCP for HPR1000 is a success. The full-flow test is an examination at the primary coolant system test stand, mimicking normal operational and extreme working conditions, to test the pump’s integrity and durability. It will be shipped to the site after being disassembled, cleaned, and packed.

 

The CNNC-made Vacuum Leak Detection Equipment for the ITER Project has Passed Acceptance Assessment

The world’s first vacuum lead detection equipment for the International Thermonuclear Experimental Reactor (ITER) project passed acceptance evaluation recently. It was made by CNNC’s Southeastern Institute of Physics. The world’s first thermal helium leak detection test was also conducted with the equipment during the assessment. Test results show that the performance was fully qualified, which sets an important baseline for the establishment of thermal helium test standards for the tokamak device in the future.

Nuclear News Weekly Roundup - 03/19 - 03/23

Hongyanhe Unit 5 RPV Delivered to Site

On March 22nd, Hongyanhe Unit 5’s reactor pressure vessel (RPV) became the first primary equipment delivered to the construction site. This marks the beginning of the peak NI equipment installation period for Hongyanhe phase II. The RPV is one of the most important components within the NI. Occupying the center of the containment building, the RPV has a height of 13 meters, a diameter of 4 meters, and weighs more than 300 tons. It houses many critical subcomponents needed to sustain and control nuclear fission, such as the reactor core, reactor internals, and control rods. Upon beginning operation, the RPV will withstand a pressure of 155 times earth’s atmosphere and very high temperatures – over 300 ℃.

 

Fuqing Unit 6’s Containment Dome Attached 10 Days Ahead of Schedule

On March 21st, ten days ahead of schedule, the containment dome for Fuqing Unit 6 (the second HPR1000 in China) was attached. The hoisting of the dome began at 6:30am using a 3200-ton crane. With a diameter of 46.8 meters, it weighs about 342 tons and also contains spray piping and a ventilation system attached inside. The dome is critical to the integrity and seal of the containment building.

 

CNECC Subsidiary Establishes JV in the UK

China Nuclear Industry Huaxing Construction Company, a major subsidiary of China Nuclear Engineering & Construction Group Corporation (CNECC), has established a joint venture – H&E Engineering Limited – with French partner Efinor. This is a solid achievement for the China nuclear industry’s  “going out” Initiative, which aims to grow industry exports. Huaxing and Efinor each hold 50% of H&E’s stocks. The new JV will focus on British nuclear market. On October 23rd, 2017, the two partners won the bid for Hinkley Point C’s HXA storage tanks and will closely follow HPC’s other tenders as well.

 

Fuqing Unit 1 Receives Top Operating Unit Score From WANO

Fuqing Unit 1’s 2017 performance received a score of “100”, the highest possible score, during a comprehensive evaluation from WANO. In 2017 CNNC had six operating units score 100, including, Tianwan Unit 2.

Nuclear News Weekly Roundup – 03/12 - 03/16

CNNC: We’ve been Thinking about Building a Regional Headquarter in Shanghai

“We’ve been thinking about building a regional headquarter in Shanghai,” CNNC President, Wang Shoujun, told journalists in a press conference during the “two sessions.” “Shanghai is the birthplace of Chinese nuclear power. The Shanghai municipality has made enormous contributions to the Qinshan NPP. Over the years, CNNC has been working closely with Shanghai Electric. In fact, CNNC’s development is not constrained to one place. Our headquarters and some R&D institutes are located in Beijing. Next, we are looking at Shanghai as an important place of support to develop and enhance the Chinese civil nuclear industry,” said Wang.

 

Qinshan and Sanmen Win Zhejiang Province’s Direct Power Sales Bid

The Development and Reform Commission of Zhejiang Province has recently released the “Notice about the Bidding Results of 2018 Direct Power Sales Pilot Platform.” According to the notice, Qinshan NPP and Sanmen NPP, two power generation enterprises with priority dispatch rights, both won direct power sales bids in Zhejiang Province. Qinshan won 10.475 billion KwH while Sanmen (still under construction) won 766 million KwH.

 

Fuqing Unit 5 Progress: Primary Pumps Reactor Internals Pass Acceptance Inspection; RCP Started Full Flow Test

On March 10th, Harbin Electric started to conduct a full flow test for Fuqing Unit 5’s RCP. The pump will be shipped to the site after the test.

 

On March 15th, the reactor internals of Fuqing Unit 5, the world’s first HPR1000, passed the acceptance inspection. The reactor internals were designed by the Nuclear Power Institute of China (NPIC) and manufactured by Shanghai Electric’s Shanghai No.1 Machine Tools Plant. Reactor internals include the primary equipment for all items inside a nuclear reactor. The system supports fuel bundles while absorbing neutrons and gamma ray emitted from the core, protecting the external materials from radiation, prolonging the lifespan of a reactor.

 

Fuqing Unit 6: Installation of Ring Crane’s Main Beam Started; Dome Will be Attached in Late March

On March 9th, the electric primary beam of the ring crane used at Fuqing Unit 6 was hoisted into place, paving the way for subsequent installation work. The ring crane is an important hoisting equipment used for installation, examination, and maintenance of devices.

 

CNPE GM Liu Wei said on March 13th that Fuqing Unit 6 is progressing smoothly. The current plan is to attach the containment dome after March 20th – sometime between 21st and 23rd, depending on the weather. Once the dome is topped off, Fuqing Unit 6 will enter the peak phase of installation.

 

Nuclear News Weekly Roundup – 03/05 - 03/09

NEA: 6-8 FCDs Planned This Year

The National Energy Administration released the 2018 Energy Work Guidance on March 7th, stating that it will continue to work on the issue of regional nuclear power curtailment. The guidance also indicates that efforts will be made to boost and support the progress of NPPs under construction. Sanmen Unit 1, Haiyang Unit 1, Taishan Unit 1, Tianwan Unit 3*, and Yangjiang Unit 5 are planned to be completed this year, which will add 6 MKW of new installed capacity. Approved NPP projects will also receive support and promotion, including 6-8 FCDs that are planned to go through this year.

Nicobar Notes: Tianwan Unit 3 has been connected to the grid since last December and began commercial operation in February 2018.

 

CNNC President Wang Shoujun: Appeal the NEA to Permit More New Builds

March 7th was the fifth day of the “two sessions,” the annual meetings of the national legislature and the top political advisory body. CNNC President Wang Shoujun told a journalist that “the Going Out of Hualong One is (only) truly realized in Pakistan. We exported three Hualong One units to Pakistan and two of them are under construction. We are having promising conversations with Argentina and Jordan and some other countries. We are being optimistic and hoping that we will sign contracts with these two countries this year... I appeal to the NEA to issue permits to new NPP projects.”

 

CNNC Increases Budget for Fuqing Unit 3 & 4

The original preliminary design budget for Fuqing Unit 3 & 4 was CNY 22.792 billion. Due to the post-Fukushima upgrades in safety standards, as well as the delay of equipment supply, the original allotted budget is proving to be inadequate to cover funds. The Electric Power Planning & Engineering Institute (EPPEI) was entrusted to evaluate the proposed changes to the original budget. The budget has been increased to CNY 24.31 billion.

 

Dongfang Electric Received Hinkley Point C’s Equipment Purchase Order

On March 1st, 2018, Dongfang Electric received equipment purchase orders for Hinkley Point C from Framatome and GE. Under those contracts, Dongfang Electric will provide steam generator supports, pressurizer supports, RCP supports, and the steam turbine generator’s LP outer casing. It marks a breakthrough for Dongfang Electric’s vision of Going Out; it is now fully capable of exporting equipment to high-end markets in developed countries.

 

Ling Long One, the CNNC Design of the SMR Demonstration Project, Passed Preliminary Design Inspection

CNNC announced that the Changjiang Small Modular Reactor (SMR) demonstration project that uses the self-developed Ling Long One (ACP100) reactor design has recently passed the preliminary design inspection. This signifies that CNNC has a firm grasp on Gen III small reactor design with complete proprietary intellectual property rights, which lays the foundation for future engineering application of SMRs.

 

China is Conducting Space Nuclear Power Studies

Liu Zhirang, Dean of China Aerospace Science and Technology Corporation’s Academy of Aerospace Propulsion Technology, introduced during the “two sessions” that the Academy is working with other Chinese design and research institutes to conduct studies on space nuclear power projects and relevant key technologies, such as nuclear heating and nuclear power. These projects are intended to expand the scope of technologies used in future space missions.

 

Nuclear News Weekly Roundup – 02/25 - 03/04

CNNC Annual Performance Meeting: More Emphasis on Marine Nuclear Projects, Sanmen Unit 1 Grid Connection Pushed to Fall 2018

At a recently-held CNNC annual performance meeting, which also introduced targets for 2018, CNNC stated that its marine nuclear projects will receive more future support. Marine development is currently a part of national strategy planning, and China now has a firm grasp on marine nuclear technology. CNNC will start work on two related items: 1) a proposal to build nuclear powered icebreaker ships for arctic exploration purposes, and 2) a separate proposal to bolster nuclear power-based applications in coastal and island locations, such as those used for heating, gas, and water. In response to Sanmen Unit 1’s progress, CNNC said that the Chinese government is being extremely cautious with the decision to allow fuel-loading as it is the world’s first AP1000 unit. Sanmen Unit 1 is expected to undergo many more rounds of testing and experimentation after the fuel load. Grid connection is projected to be accomplished by fall 2018 or in early 2019. 

 

SPIC Approved to Compile the New IEC 63186 Standards on NPP Seismic Outage System Design

Shanghai Nuclear Engineering Research and Design Institute (SNERDI), the R&D subsidiary of SPIC, was recently approved to compile the new International Electrotechnical Commission’s 63186 NPP Standards – Important Safety Instrumentation and Control Systems – Seismic Outage System Design Recommendations. Contributing to the international standards of the ISO and IEC is a significant breakthrough for the Chinese nuclear industry. It also marks the Chinese nuclear industry’s switch from being a mere follower in this field to becoming a leader.

 

Jiangsu ENTC Nuclear Technology Won the Bid to Supply Taishan Unit 2’s NI Mechanical Seal Materials

Jiangsu ENTC Nuclear Technology announced recently that it won both first and second section project bids to supply mechanical seal materials for the nuclear island (NI) of Taishan Unit 2. The contract is with Taishan Nuclear Power Joint Venture Company, Taishan NPP’s operation and management (O&M) company co-invested by CGN, EDF, and Guangdong YUDEAN Group. This was also the first bid of its type (large displacement piping for the biological shield) to be fully localized, signaling the end of only foreign companies dominating this area of the market.

 

Hongyanhe NPP’s Active Radiation Monitoring System Passes NNSA Inspection

On February 26th, the Northeast Nuclear and Radiation Inspection Station of the Ministry of Environmental Protection (MEP) held an examination conference for Hongyanhe NPP’s active radiation monitoring system on behalf of the NNSA. The inspection group conducted a comprehensive examination by reviewing documents, holding site surveys, reviewing items monitored, and interviewing NPP staff. The conference concluded with the active radiation monitoring system passing the inspection and receiving the greenlight to begin operation.

 

Fuqing Unit 5 & 6 Had a Successful First Backfeeding

On March 2nd, CNNC’s HPR1000 demonstration project, Fuqing Unit 5 & 6 underwent a successful first-time 220 kV backfeeding. This has set the stage for subsequent installation and commissioning work. Power backfeeding is usually needed during the later stages of power station construction when consuming large amounts of power prior to power generation.